Oct. 15, 2020, 6:19 p.m. EDT

Turquoise Hill announces third quarter 2020 production and provides updates on underground development, the definitive estimate and the liquidity outlook

new
Watchlist Relevance
LEARN MORE

Want to see how this story relates to your watchlist?

Just add items to create a watchlist now:

or Cancel Already have a watchlist? Log In

MONTREAL, Oct. 15, 2020 (Canada NewsWire via COMTEX) -- Turquoise Hill Resources Ltd. ("Turquoise Hill" or the "Company") today announced third quarter 2020 production for Oyu Tolgoi and provided an update on underground development, COVID-19 and the definitive estimate.

Q3' 2020 Highlights







        
            --  Copper and gold production guidance for 2020 remains within the
                ranges of 140,000 to 170,000 tonnes and 155,000 to 180,000
                ounces respectively, with gold production trending towards the
                higher end of the range.
            --  Limited flights adhering to Mongolian protocols allowing
                expatriates to return to Mongolia began in July.
            --  Access to higher copper and gold grades is expected to continue
                for the remainder of 2020, and into 2021.
            --  C1 cash costs(1) guidance remains in the $1.60 - $2.00 range.
            --  The 2020 operating cash cost estimate remains in a range
                between $780 million - $830 million.
            --  Capital expenditure for 2020 on a cash-basis for open-pit
                operations is trending toward the lower end of the $70 million
                - $90 million range.
            --  TRQ now expects to have sufficient liquidity to meet its
                requirements, including for its operations and underground
                development, into Q2 2022.
        
        
        


Q3' 2020 Production







        
            --  Q3' 2020 mill throughput was slightly higher than Q3' 2019 due
                to slightly higher mill availability and an increased milling
                rate associated with softer ore.
            --  Copper production of 36,286 tonnes, an increase of 28% vs Q3'
                2019, was due to a planned increase in head grade as the open
                pit moves deeper into the higher grade Phase 4B.
            --  On a sequential basis, Q3' 2020 Copper production was slightly
                lower driven by a decrease of copper head grade as central ore
                proportion in the ore blend to the crusher was decreased.
            --  Gold production of 36,743 ounces, an increase of 43% vs Q3'
                2019 due to increased head grade as the open pit moves deeper
                into the higher grade Phase 4B.
        
        
        








        
        
             _______________________________
        
        
                         (1) C1 cash costs are a non-GAAP (Generally Accepted
                          Accounting Principles) measure (i.e. not defined by
                          International Financial Reporting Standards (IFRS)). It
                          is presented in order to provide investors and other
                          stakeholders with an additional understanding of
                          performance and operations at the Oyu Tolgoi mine and
                          is not intended to be used in isolation form, or as a
                          replacement for, measures prepared in accordance with
                          IFRS. Please refer to Non-GAAP Measures section of the
                          Company's Q2 MD&A for further information.
        
        
        


Oyu Tolgoi underground project







        
            --  Work on the project has continued to progress despite COVID-19
                controls and ongoing international travel restrictions issued
                by the Government of Mongolia. 40 expatriates returned to
                Mongolia in July - the first time this has been possible since
                the onset of the pandemic. Further flights are planned in order
                to return the required specialists to site.
        
            --  Care and maintenance activities continue at shafts 3 and 4 but
                some commissioning activities have advanced in preparation for
                shaft sinking, including rope installation and no-load testing
                of the Shaft 4 hoisting system. Further substantial progress
                will require the remobilisation of international shaft-sinking
                specialists, and subject to local border restrictions,
                preparation is underway to mobilise these contractors before
                the end of the fourth quarter 2020. Review of the impacts of
                the shaft 3 and 4 delays are ongoing, but first sustainable
                production for Panel 0 is not anticipated to be affected. We
                will communicate any implications, particularly for Panel 1 and
                Panel 2 ramp-up which shaft 3 and 4 support, at an appropriate
                time.
        
            --  Overall, underground lateral development has now reached 48,604
                equivalent metres, and progress continues broadly in line with
                the OTTR20 Technical Report.
        
            --  All surface infrastructure required for first sustainable
                production is complete and the team is focused on the safe and
                efficient delivery of the critical underground Material
                Handling System 1 (MHS1). The balance of project infrastructure
                to be delivered post the completion of MHS1 is not needed for
                first sustainable production; however, it is needed to support
                the production ramp-up profile and the life of mine material
                handling infrastructure capacity.
        
            --  In the fourth quarter of 2020, the definitive estimate cost and
                schedule update for Panel 0 is expected, and as advised by the
                manager, preliminary indications from the definitive estimate
                process are that first sustainable production is trending
                towards the earlier months of the previously guided range of
                October 2022 to June 2023, and that the forecast development
                capital cost remains within the range of $6.6 to $7.1 billion.
                This is subject to ongoing internal assessment and review as
                part of finalising the definitive estimate process by the
                manager. Turquoise Hill is undertaking an independent technical
                assurance review into the indications and findings of the
                definitive estimate communicated by the manager.
        
            --  As part of its ongoing review, Turquoise Hill has received an
                independent consultant's report with respect to the delay and
                cost overruns at OT, which were announced by the Company in
                July 2019. The management and independent directors of the
                Company are currently reviewing the report with their advisors.
        
            --  Due to the ongoing nature of the COVID-19 pandemic, its full
                impact remains unknown. The cost and schedule range assumes an
                easing of travel restrictions and COVID-19 related controls
                from the time of reporting, which will continue to be monitored
                and reviewed.
        
        
        


Liquidity Outlook

TRQ regularly reviews its available liquidity and short-term cash flow forecasts as information changes or becomes available. An updated liquidity forecast will be included in TRQ's third quarter earnings release on November 13, 2020. However, based on an initial review, which takes into account higher commodity prices as well as updated assumptions regarding delays in underground capital expenditure caused by COVID-related travel and other restrictions, TRQ now expects to have sufficient liquidity to meet its requirements, including for its operations and underground development, into Q2 2022. Further updates to its liquidity forecast will be provided by the Company as and when available.

Oyu Tolgoi Production Data

All data represents full production and sales on a 100% basis







        
        
                 3Q
                4Q
               1Q    2Q    3Q
             9 months
             9 months
             Full Year
        
        
                                                        2019     2019     2020   2020   2020            2020             2019               2019
        
        
        
        
        
        
             Open pit material mined ('000 tonnes)   24,844   28,122   26,834 23,218 23,979          74,032           73,195            101,316
        
        
        
             Ore treated ('000 tonnes)               10,040   11,088   10,889  9,645 10,072          30,606           29,689             40,777
        
        
        
             Average mill head grades:
        
        
        
             Copper (%)                               0.37     0.42     0.42   0.47   0.45            0.45             0.46               0.45
        
        
        
             Gold (g/t)                                0.14     0.15     0.15   0.19   0.21            0.18             0.34               0.29
        
        
        
             Silver (g/t)                              1.03     1.06     1.14   1.22   1.22            1.19             1.16               1.13
        
        
        
             Concentrates produced ('000 tonnes)      131.3    152.6    164.5  169.9  168.5           502.9            552.1              674.6
        
        
        
             Average concentrate grade (% Cu)          21.7     21.6     21.4   21.5   21.5            21.5             21.7               21.7
        
        
        
             Production of metals in concentrates:
        
        
        
             Copper ('000 tonnes)                      28.4     32.9     35.2   36.5   36.3           108.0            113.4              146.3
        
        
        
             Gold ('000 ounces)                          26       24       26     31     37              94              218                242
        
        
        
             Silver ('000 ounces)                       191      190      214    212    219             645              677                867
        
        
        
             Concentrate sold ('000 tonnes)           157.0    157.5    125.9  194.3  167.9           488.1            567.2              724.7
        
        
        
             Sales of metals in concentrates:
        
        
        
             Copper ('000 tonnes)                      32.4     32.3     25.8   39.7   34.4            99.9            117.6              149.9
        
        
        
             Gold ('000 ounces)                          35       25       20     31     34              84              249                274
        
        
        
             Silver ('000 ounces)                       207      244      146    220    201             566              652                896
        
        
        
             Metal recovery (%)
        
        
        
             Copper                                    75.1     74.2     74.3   79.1   78.9            77.4             80.3               78.7
        
        
        
             Gold                                      54.7     48.2     46.0   52.0   53.7            51.0             66.2               63.6
        
        
        
             Silver                                    56.0     53.5     51.5   55.8   54.6            54.0             59.6               58.1
        
        
        


Class Action Complaint

On October 14, 2020, a class action complaint was filed in the U.S. District Court, Southern District of New York against the Company, certain of its current and former officers as well as Rio Tinto and certain of its officers. The complaint alleges that the defendants made material misstatements and material omissions with respect to, among other things, the schedule, cost and progress to completion of the development of Oyu Tolgoi in violation of Section 10(b) of the U.S. Securities Exchange Act and Rule 10b-5 thereunder. The Company believes that the complaint against it is without merit.

Forward-looking statements and forward-looking information

Certain statements made herein, including statements relating to matters that are not historical facts and statements of the Company's beliefs, intentions and expectations about developments, results and events which will or may occur in the future, constitute "forward looking information" within the meaning of applicable Canadian securities legislation and "forward-looking statements" within the meaning of the "safe harbor" provisions of the United States Private Securities Litigation Reform Act of 1995. Forward-looking statements and information relate to future events or future performance, reflect current expectations or beliefs regarding future events and are typically identified by words such as "anticipate", "could", "should", "expect", "seek", "may", "intend", "likely", "plan", "estimate", "will", "believe" and similar expressions suggesting future outcomes or statements regarding an outlook. These include, but are not limited to, statements and information regarding: the completion and potential benefits of the share consolidation; the expectations set out in the 2020 Oyu Tolgoi Technical Report ("OTTR20"); the timing and amount of future production and potential production delays; statements in respect of the impacts of any delays on the Company's cash flows; expected copper and gold grades; liquidity, funding sources, funding requirements and planning and the status and nature of the Company's ongoing discussions with Rio Tinto plc and its subsidiaries with respect to future funding plans and requirements (including as contemplated by the Memorandum of understanding dated September 9, 2020 (the "MoU")); the amount of any funding gap to complete the Oyu Tolgoi underground project; the amount and potential sources of additional funding; the Company's ability to re-profile its existing project debt in line with current cash flow projections; the amount by which a successful re-profiling of the Company's existing debt would reduce the Company's currently projected funding requirements; the Company's and Rio Tinto's understanding regarding the raising of supplemental senior debt and the Company's ability to raise supplemental senior debt; the Company's and Rio Tinto's understanding regarding the process for identifying and considering other funding options; the Company's and Rio Tinto's understanding regarding the scope and timing for an equity offering by the Company to address any remaining funding gap; the Company's intention to prioritize funding by way of debt and/or hybrid financing over equity funding; the Company's expectation of the anticipated funding gap; the timing of studies, announcements and analyses; status of underground development; the mine design for Panel 0 of Hugo North Lift 1 and the related cost and production schedule implications; the re-design studies for Panels 1 and 2 of Hugo North Lift 1 and the possible outcomes, content and timing thereof; expectations regarding the possible recovery of ore in the two structural pillars to the north and south of Panel 0; the possible progression of a state-owned power plant ("SOPP") and related amendments to the Power Source Framework Agreement ("PSFA") as well as power purchase agreements; the timing of construction and commissioning of the potential SOPP; sources of interim power; the potential impact of COVID-19 on the Company's business, operations and financial condition; capital and operating cost estimates, timing of completion of the Definitive Estimate review and the scope thereof; mill and concentrator throughput; the outcome of formal international arbitration proceedings; anticipated business activities, planned expenditures, corporate strategies, and other statements that are not historical facts.

Forward-looking statements and information are made based upon certain assumptions and other important factors that, if untrue, could cause the actual results, performance or achievements of the Company to be materially different from future results, performance or achievements expressed or implied by such statements or information. There can be no assurance that such statements or information will prove to be accurate. Such statements and information are based on numerous assumptions regarding present and future business strategies, local and global economic conditions, and the environment in which the Company will operate in the future, including the price of copper, gold and silver; projected gold, copper and silver grades; anticipated capital and operating costs, anticipated future production and cash flows; the anticipated location of certain infrastructure in Hugo North Lift 1; sequence of mining within and across panel boundaries; the availability and timing of required governmental and other approvals for the construction of the SOPP; the ability of the Government of Mongolia to finance and procure the SOPP within the timeframes anticipated in the PSFA, as amended; the willingness of third parties to extend existing power arrangements; the status of the Company's relationship and interaction with the Government of Mongolia on the continued operation and development of the Oyu Tolgoi mine and Oyu Tolgoi LLC internal governance; the status and nature of the Company's ongoing discussions with Rio Tinto plc and its subsidiaries with respect to future funding plans and requirements (including as contemplated by the MoU) as well as the completion and potential benefits of the share consolidation. Certain important factors that could cause actual results, performance or achievements to differ materially from those in the forward-looking statements and information include, among others: copper, gold and silver price volatility; discrepancies between actual and estimated production; mineral reserves and resources and metallurgical recoveries; development plans for processing resources; the outcome of the Definitive Estimate review; public health crises such as COVID-19; matters relating to proposed exploration or expansion; mining operational and development risks, including geotechnical risks and ground conditions; litigation risks; regulatory restrictions (including environmental regulatory restrictions and liability); Oyu Tolgoi LLC or the Government of Mongolia's ability to deliver a domestic power source for the Oyu Tolgoi project within the required contractual time frame; communications with local stakeholders and community relations; activities, actions or assessments, including tax assessments, by governmental authorities; events or circumstances (including strikes, blockades or similar events outside of the Company's control) that may affect the Company's ability to deliver its products in a timely manner; currency fluctuations; the speculative nature of mineral exploration; the global economic climate; dilution; share price volatility; competition; loss of key employees; cyber security incidents; additional funding requirements, including in respect of the development or construction of a long-term domestic power supply for the Oyu Tolgoi project; capital and operating costs, including with respect to the development of additional deposits and processing facilities; and defective title to mineral claims or property. Although the Company has attempted to identify important factors that could cause actual actions, events or results to differ materially from those described in forward-looking statements and information, there may be other factors that cause actions, events or results not to be as anticipated, estimated or intended. All such forward-looking statements and information are based on certain assumptions and analyses made by the Company's management in light of their experience and perception of historical trends, current conditions and expected future developments, as well as other factors management believes are reasonable and appropriate in the circumstances. These statements, however, are subject to a variety of risks and uncertainties and other factors that could cause actual events or results to differ materially from those projected in the forward-looking statements or information.